Projects & Case Studies

Proof, project by project

A selection of completed installations across Iowa — the scope, the challenge, and how we delivered.

Downtown Des Moines Office Tower BuildoutCommercial Office

Des Moines, IA

Downtown Des Moines Office Tower Buildout

850 · CAT6A drops48-strand OM4 · Fiber backbone14 weeks · Duration
Scope
Full structured cabling for a 12-story Class-A office tower — horizontal copper, fiber riser backbone, and three telecom rooms per floor.
Challenge
Four tenant move-in dates stacked across eight weeks, with floors still under active construction above completed spaces.
Solution
Phased floor-by-floor installation with dedicated crews per stack, pre-terminated fiber risers, and nightly coordination with the GC’s superintendent.
  • All four tenants moved in on schedule
  • 100% of links passed certification on first test
  • Zero punch-list items at turnover
Regional Hospital Network ModernizationHealthcare

Central Iowa

Regional Hospital Network Modernization

1,200 · Outlets replaced22 nights · Cutover windows0 minutes · Unplanned downtime
Scope
Replacement of aging Category 5e infrastructure across a 240-bed hospital, including redundant fiber between six IDFs and the main data room.
Challenge
A facility that operates 24/7 — no wing could lose network connectivity for more than a four-hour window, ever.
Solution
ICRA-trained crews working night shifts, parallel new infrastructure built alongside legacy, and rehearsed cutovers executed wing by wing.
  • Zero unplanned outages across the project
  • Redundant fiber paths to every IDF
  • Full as-built documentation delivered to facilities
K-12 District-Wide Cabling RefreshEducation

Des Moines Metro

K-12 District-Wide Cabling Refresh

2,400 · Cable runs310 · Access points2 weeks early · Schedule
Scope
Six schools re-cabled over one summer — classroom drops, wireless access points, security cameras, and paging systems.
Challenge
A 10-week summer window with hard deadlines: every building had to be ready for teachers returning in August.
Solution
Three crews running parallel buildings, standardized labeling across the district, and weekly progress reporting to the district’s technology director.
  • All six schools ready two weeks early
  • Wi-Fi coverage gaps eliminated in every classroom
  • District-wide labeling standard adopted
Colocation Data Center White-Space BuildData Center

Urbandale, IA

Colocation Data Center White-Space Build

576 · Fiber strands96 · Cabinets cabled20,000 sq ft · White space
Scope
Structured fiber and copper for 20,000 sq ft of new white space — MPO trunk fiber, overhead tray, and cabinet-to-cabinet connectivity.
Challenge
High-density design requiring 40Gb-ready fiber to every cabinet row, installed while adjacent suites stayed live.
Solution
Pre-tested MPO trunk assemblies, containment-friendly overhead pathway, and OTDR certification of every strand before handoff.
  • 40Gb-ready fiber to all 96 cabinets
  • Every strand certified with reports delivered
  • Expansion-ready trunk capacity built in
Manufacturing Plant Low-Voltage OverhaulIndustrial

Ames, IA

Manufacturing Plant Low-Voltage Overhaul

2,100 ft · Cable tray180 · Floor drops0 · Production stoppages
Scope
Plant-wide cabling for a 180,000 sq ft manufacturing facility — cable tray, ruggedized drops to the floor, cameras, and Wi-Fi for scanners.
Challenge
Production ran two shifts, six days a week. Work had to thread between lines without stopping a single one.
Solution
Sunday installation windows, pre-fabricated tray sections, and armored cable in high-traffic zones — sequenced bay by bay with plant engineering.
  • Zero production interruptions
  • Scanner dead zones eliminated plant-wide
  • Abandoned legacy cable fully removed
Municipal Government Center CablingGovernment

Polk County, IA

Municipal Government Center Cabling

420 · Drops6 · Secure areas0 · Change orders
Scope
Complete low-voltage infrastructure for a new municipal building — offices, council chambers AV, secure areas, and public Wi-Fi.
Challenge
Strict procurement requirements, background-checked crews for secure areas, and full documentation required for public records.
Solution
Prevailing-wage compliant crews, segregated secure-area pathways, and a documentation package built to survive any audit.
  • Delivered within the public bid schedule
  • Secure and public networks fully segregated
  • As-builts accepted by the county on first submission